MALABAR HILLS

MALABAR HILLS
MALABAR HILLS
show 17 more

Certificates related to project:

Orders related to project:

Information As Of: 06/04/2026

Financial Progress: 72.00%


Physical Progress: 96.00


Available Units: 21/75


By
KAKKOTH , PERINTALMANNA
 Malappuram
In Progress
Proposed Completion On28, Nov 2026
Project Related Important Documents
Main Documents (5)
Plan & Brochures (1)
Quick Facts
Total Floor Area Under Residential Use : 0 sqm Total Floor Area Under Other Use: 0 sqm
Common AmenitiesProposed - Percentage
Letter boxNO - 0%
Reticulated Gas SupplyNO - 0%
Servant's room with attached toiletNO - 0%
Water conservation, Rain water harvestingNO - 0%
Landscaping & Tree plantingYES - 100%
Open parkingYES - 70%
Sign BoardsYES - 100%
Treatment and disposal of sewage and sullage waterYES - 100%
Water supplyYES - 70%
Aggregate area of recreational open spaceNO - 0%
Driver's room with attached toiletNO - 0%
Electrical meter room, Sub-station, Receiving stationNO - 0%
Energy ManagementNO - 0%
Public health servicesNO - 0%
Solar systemsNO - 0%
Solid waste management and disposalYES - 70%
Community buildingsNO - 0%
Fire protection and Fire safety requirementsNO - 0%
Intercom facilityNO - 0%
Outdoor gathering pavilionNO - 0%
Sewerage (Chamber, Lines, Septic tank, STP)NO - 0%
Storm water drainsNO - 0%
Visitors ParkingNO - 0%
Guest Suite : YES - 70%
Association room : YES - 100%
Street lighting : YES - 70%
Indoor Games Room : YES - 100%
Security cameras : YES - 100%
Internal Roads & Footpaths : YES - 75%