Information As Of: 08/04/2026
Financial Progress: 75.00%
Physical Progress: 95.00
Available Units: 0/83
Calicut Bye Pass Road , PALAKKAD-2
Palakkad
83 Residential Units
0 Commercial Units
In Progress Proposed Completion On31, Dec 2027
10 Unit Types In Jayaraj Srishti Block B (75 Units / 75 Units Booked)
1 Unit Types In Jayaraj Srishti Block A (8 Units / 8 Units Booked)
Project Related Important Documents
Main Documents (5)
Plan & Brochures (2)
Separate bank Account - Withdrawal Forms (3)
Quick Facts
Total Floor Area Under Residential Use : 15806.10 sqm Total Floor Area Under Other Use: 0 sqm
| Common Amenities | Proposed - Percentage |
|---|---|
| Water conservation, Rain water harvesting : | YES - 95% |
| Community buildings : | NO - % |
| Fire protection and Fire safety requirements : | YES - 95% |
| Sewerage (Chamber, Lines, Septic tank, STP) : | YES - 95% |
| Storm water drains : | YES - 95% |
| Street lighting : | NO - % |
| YES - 100% | |
| Visitors Parking : | YES - 90% |
| Landscaping & Tree planting : | NO - % |
| Open parking : | NO - % |
| Treatment and disposal of sewage and sullage water : | YES - 100% |
| Water supply : | YES - 95% |
| Aggregate area of recreational open space : | YES - 85% |
| Electrical meter room, Sub-station, Receiving station : | YES - 85% |
| Energy Management : | NO - % |
| Internal Roads & Footpaths : | NO - % |
| Public health services : | NO - % |
| Solid waste management and disposal : | YES - 100% |